Green Line Transformation Weekly Progress Update: December 6 – December 11
Updated on December 11, 2020
GLT projects will improve safety, reliability, and access for Green Line riders and the surrounding communities.
- Lechmere Viaduct Rehabilitation – 45% complete
- Green Line D Track and Signal Replacement – 76% completion at Chestnut Hill, 95% completion at Beaconsfield, and 100% completion in the Reservoir area, Newton Centre, and Waban
Crews are installing a temporary platform at Newton Highlands until the station is upgraded with the Newton Highlands Accessibility project. Track and signal work will also take place in this area starting next week.
Building a Better T
As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.
Related Projects
Building a Better T
As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.