Red Line Transformation Weekly Progress Update: December 12 – 17
Updated on December 17, 2021
RLT projects will improve safety, reliability, and access for Red Line riders and the surrounding communities.
Last week, work continued on the following projects:
- Cabot Yard and Maintenance Facility – 30% complete
- Red Line Signal Upgrade – 16% complete