Green Line Transformation Weekly Progress Update: October 24 – 30
Updated on October 30, 2020
The Green Line Program will improve safety, reliability and access for Green Line riders and the surrounding communities.
- Lechmere Viaduct Rehabilitation – 32% complete
- Fenway Portal Flood Protection – 87% complete
- Green Line D Track and Signal Replacement – 47% completion at Chestnut Hill, 80% completion in the Reservoir area, and 95% completion at Beaconsfield
Building a Better T
As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.