Green Line Transformation Weekly Progress Update: February 14 – 19
Updated on February 19, 2021
GLT projects will improve safety, reliability, and access for Green Line riders and the surrounding communities.
Crews began site preparation work for the B Branch Consolidation on Monday, February 15. The project is now at 2% completion.
On the Lechmere Viaduct, crews installed structural support for the walkways and floors, and construction is now 54% complete.