Green Line Transformation Weekly Progress Update: September 26 – October 2
Updated on October 2, 2020
GLT projects will improve safety, reliability and access for Green Line riders and the surrounding communities.
- B Branch Track and Intersection Upgrades – 100% complete
- Lechmere Viaduct Rehabilitation – 28% complete
- Green Line D Track and Signal Replacement – 18% completion at Chestnut Hill, 72% completion in the Reservoir area, and 95% completion at Beaconsfield