Skip to main content
Menu

Capital Transformation Programs 2022 Year in Review

Updated on December 21, 2022

Watch the 2022 Year in Review (Spanish)

As 2022 comes to an end, we’re looking back at the accomplishments the Green Line, Orange Line, and Red Line Transformation teams achieved this year.

We appreciate the cooperation and understanding of all our riders and the communities we serve as we work to improve the Green, Orange, and Red Lines.

Download the 2022 Year in Review PDF

Jump to a section below:


Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Green Line Transformation 2022 Accomplishments

This year we completed two large construction projects critical to Green Line infrastructure that aim to improve the safety and reliability of the system. Our team also progressed projects in the design phase that will further improve the accessibility of the Green Line.

Green Line Track and Intersection Upgrades (2022)

big trucks on tracks going down into a tunnel, you can see the citgo sign in the background

Status: Complete

Over the summer, the GLT team completed 12-day full access closures on the B and C Branches and a 16-day full access closure on the E Branch to install equipment for the Green Line Train Protection System (GLTPS) and upgrade track. This fall, the team conducted 25 days of full access on the D Branch, separated into three separate closures, for GLTPS equipment installation and track upgrades.

Throughout these closures, crews replaced over 14,000 feet of track, 10 pedestrian crossings, and installed over 200 components of GLTPS wayside equipment across all four branches of the Green Line.

Learn More about the Green Line Track Upgrades (2022)

Lechmere Viaduct Rehabilitation

a green line train at science park station on a blue sky day

Status: Complete

Crews rehabilitated and replaced track on the historic Lechmere Viaduct, which carries Green Line trains across the Charles River and into downtown Boston. These upgrades strengthened the structure of the viaduct while preserving its facade and improved the service reliability between downtown Boston and Somerville.

In May 2020, the bridge was closed to support work on both the Lechmere Viaduct Rehabilitation and the Green Line Extension (GLX) project. Service between Science Park and Lechmere Stations resumed in March, along with the opening of the GLX Union Square branch. The Medford/Tufts branch opened for service in December.

Learn more about the Lechmere Viaduct Rehabilitation

Brookline Hills Station Accessibility Improvements

a green line trolley at brookline hills station in the snow

Status: Complete

In January, Brookline Hills Station reopened after the MBTA completed accessibility improvements. The team implemented these upgrades in coordination with the Town of Brookline and the Brookline High School Expansion project.

The improvements made at Brookline Hills further progressed the overall accessibility of the D Branch, and the upgrades are similar to what riders can expect from the D Branch Station Accessibility Improvements. Crews raised the platform heights, constructed accessible crosswalks and pedestrian pathways, and improved customer experience through upgraded lighting, signage, and security measures.

Learn more about the Brookline Hills Station Accessibility Improvements

D Branch Station Accessibility Improvements

a labelled diagram showing where lighting, bike shelter, emergency call box, and new accessible parking spaces will be located at Waban station

Status: In Progress

This year, the GLT team reached the 75% design milestone for the D Branch Station Accessibility Improvements project and is approaching completion of the design.

A pre-construction public meeting will be held next year to provide the public with more information on the planned improvements, the construction schedule, and mitigation strategies.

Construction on Waban, Eliot, Chestnut Hill, and Beaconsfield stations is scheduled to begin next year. These improvements will make the D Branch the first fully accessible branch on the Green Line.

Learn more about the D Branch Station Accessibility Improvements

Newton Highlands Station Accessibility Improvements

a rendering of future accessible ramp at newton highlands station platform

Status: In Progress

The Newton Highlands Station Accessibility Improvements project approached design completion. Our team has continued to coordinate with the City of Newton, the Newton Commission on Disability, and the Newton Historical Commission to progress the design plans.

The project team will hold a public meeting next year to present the design to the community and to discuss the next steps moving forward as we approach construction.

Learn more about Newton Highlands Station Accessibility Improvements

Symphony Station Accessibility Improvements

a rendering of future symphony station tower entrance

Status: In Progress

This year, the GLT team approached completion of the design for the Symphony Station Accessibility Improvements project and began preparations for utility relocation work.

In 2023, utility relocation work will begin as the area is prepared for future construction of the elevators that will provide access to Symphony Station.

Learn more about Symphony Station Accessibility Improvements


Orange Line Transformation 2022 Accomplishments

In 2022, we completed a shutdown of the entire Orange Line, making critical improvements to return the system to a state of good repair.

We also continued rebuilding the Wellington Yard and Maintenance Facility, upgrading Orange Line Signals, and upgrading the traction power substations.

Orange Line 30-Day Surge

seven photos of crew members doing work on various parts of the orange line

Status: Complete

From August 19 to September 18, Orange Line service was shut down so that crews had full access to complete critical safety and infrastructure upgrades and address safety directives from the Federal Transit Authority (FTA).

Over the course of these 30 days, teams were able to complete five years of work, improving track and signal infrastructure, station amenities, and new vehicle readiness. Crews replaced over 3,500 feet of track, 14,000 linear feet of rail, 20 units of special trackwork, 48,000 feet of signal cable, and installed Cologne Eggs near Tufts Medical Center Station. Teams completed two successful cutovers from the old signal system to the new system at Oak Grove and Malden Center. Additionally, service returned with all new Orange Line vehicles.

Learn more about the Orange Line 30-Day Surge

Wellington Yard and Maintenance Facility

crews working on a stretch of track rail outdoors

Status: Substantially Complete

Upgrades to Wellington Yard and Maintenance Facility will increase service capacity and deliver safer, cleaner operations to all riders.

Crews have substantially completed the trackwork in the yard and have addressed all final punch list items. In the maintenance facility, crews have completed track replacement and modernized the vehicle facility to improve vehicle maintenance and reduce downtime.

Learn more about Wellington Yard and Maintenance Facility

Orange Line Signal Upgrades

four people in hard hats and reflective vests looking at a switchboard on the wall

Status: In Progress

The signal system is being modernized and replaced with new digital infrastructure that will improve service reliability, reduce headways, and renew the lifespan for the entire system.

This year, crews completed two successful cutovers to the new system at Oak Grove and Malden Center stations. These cutovers were completed during the 30-day Orange Line Surge. Crews are continuing to install and test new signal infrastructure at Sullivan Square and Community College.

Learn more about Orange Line Signal Upgrades

Orange Line Traction Power Substation Upgrades

a wall of signals, buttons, and switches

Status: In Progress

Crews are currently working at Oak Grove to upgrade the traction power substation with new facilities and equipment, improving remote operation of the substation. Crews are installing a new communication circuit, and engineers began testing new software for the substations.

The new software will integrate with the MBTA’s existing communications system, and the new circuit will allow engineers to perform live testing of this software.

Learn more about Orange Line Traction Power Substation Upgrades


Red Line Transformation 2022 Accomplishments

The Red Line Transformation (RLT) team is working on the Red Line Signal Upgrades and have completed four successful cutovers from the old system to the new system. We've also completed the design for the Codman Yard Expansion and Improvements, and mobilization for construction has started.

Red Line Signal Upgrades

a crane placing a signal building by tracks at sunset

Status: In Progress

The Red Line signal system is being modernized and replaced with new digital infrastructure that will improve service reliability, reduce headways, and renew the lifespan for the entire system.

This year, crews completed four successful cutovers to the new system at Alewife, Davis, Porter, and Harvard stations. Crews are actively testing signal infrastructure at Central, Park, Downtown Crossing, Quincy Adams, Davis, Porter, and Ashmont stations.

Learn more about Red Line Signal Upgrades

Cabot Yard and Maintenance Facility

active construction inside cabot garage, there's construction materials everywhere and a red line train up on riser to the left

Status: In Progress

Updates continue at the Cabot Yard and Vehicle Maintenance Facility to improve safety, reliability, and service capacity by enhancing our maintenance operations.

At Cabot Yard, crews are working on drainage and duct banks, and are returning upgraded tracks to regular operation. To allow continued operation of the yard, only two tracks are taken out of service at a time.

At the Cabot Maintenance Facility, crews continue work on the installation of HVAC, electrical, and roofing upgrades in preparation for winter weather.

Learn more about Cabot Yard and Maintenance Facility

Codman Yard Expansion and Improvements

a person in a reflective rain jacket in front of many red line trains in a train yard. it's dark and rainy

Status: In Progress

This past spring, the RLT team completed the final design for the Codman Yard Expansion and Improvements and the team held two public meetings: one in March to discuss the final design plans, and one pre-construction meeting in October to discuss the construction plans and project schedule.

We have met with several community groups in the area throughout this process and will continue to do so as the project progresses. The improvements made to Codman Yard will benefit all Red Line riders and the members of the surrounding community.

The project team was given the notice to proceed in November, and construction is scheduled to begin in early 2023.

Learn more about Codman Yard Expansion and Improvements


Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects