MBTA Makes Further Progress on Expedited Critical Track Work on Orange Line, Removes Seven Speed Restrictions
Posted on March 25, 2024
Four speed restrictions also removed on the Red Line last week.
The MBTA today announced the completion of critical track work on the Orange Line. Crews accomplished this critical work due to unencumbered access to track areas while Orange Line service was suspended between Jackson Square and North Station for four days from March 18-21. As a result, six safety-related speed restrictions were removed last week with a seventh removed over the weekend following final completion work.
“With each step, we are following through on our commitment to rebuild our tracks to give our riders the improved reliable trip they deserve. I’m proud of the dedicated workforce that worked in a short window of time while delivering on significant work along the Orange Line corridor,” said MBTA General Manager and CEO Phillip Eng. “There is much more to do, and we are determined to make tough decisions to prioritize work while balancing the need to ensure the public has sufficient options to use mass transportation alternatives. We thank riders for their patience and understanding as we continue reinvesting in our infrastructure and make important progress to give them a system that they can rely on and be proud of.”
The important work accomplished on the Orange Line means riders will experience a more reliable trip with fewer unplanned service disruptions related to older tracks, older infrastructure, signal issues, or power problems. Riders will also be provided with a safer ride as a result of this state of good repair work.
With unencumbered access to Orange Line stations, crews were able to accomplish critical work and maximize access to tracks and stations in a number of ways:
- More than 5,000 feet of rail was installed.
- 27 cologne egg rail fasteners were replaced.
- 63 rail “shoulders” were cored.
- Nearly 260 plates were installed.
- 10 switch timbers embedded in concrete were replaced by the Maintenance of Way team.
- 500 feet of stringer cable was replaced.
- Nine third rail insulators were replaced by the Maintenance of Way team.
- Critical switch and crossover work was accomplished.
- Tunnel inspections were performed between State and Haymarket.
- Structural overhead inspections of stations were accomplished at Chinatown, Massachusetts Avenue, Ruggles, and Roxbury Crossing with additional station entrance inspections performed.
- Concrete slab sections were replaced within the State station “Rainbow Corridor.”
- Station inspections were accomplished between Jackson Square and Downtown Crossing.
- Modernization work along the southwest corridor between Roxbury Crossing and Chinatown was performed with concrete coring accomplished in eight locations.
- Security and emergency management enhancements were performed at Downtown Crossing.
- Crews performed visual surveys and measurements of tunnels, communication rooms, and emergency exits from Ruggles to State in support of the MBTA’s Statewide Radio System cable installation path. Crews also surveyed Station Communication rooms and public areas for radio equipment installations as the crew progressed from station to station through the tunnels.
As a result of this critical work, the following safety-related speed restrictions are no longer in place:
Speed Restriction Number | Restriction Information and Location | Status | |||
---|---|---|---|---|---|
Speed Restriction Number | 1. 526479 | Restriction Information and Location | Northbound between Ruggles and Massachusetts Avenue | Status | Removed |
Speed Restriction Number | 2. 000045 | Restriction Information and Location | Northbound at Back Bay | Status | Removed |
Speed Restriction Number | 3. 523874 | Restriction Information and Location | Northbound between Back Bay and Tufts Medical Center | Status | Removed |
Speed Restriction Number | 4. 523882 | Restriction Information and Location | Northbound between Tufts Medical Center and Chinatown | Status | Removed |
Speed Restriction Number | 5. 000055 | Restriction Information and Location | Southbound at Chinatown | Status | Removed |
Speed Restriction Number | 6. 000061 | Restriction Information and Location | Northbound at Back Bay | Status | Removed |
Speed Restriction Number | 7. 000002 | Restriction Information and Location | Northbound between Tufts Medical Center and Chinatown | Status | Removed |
Additionally, four speed restrictions were removed on the Red Line last week:
Speed Restriction Number | Restriction Information and Location | Status | |||
---|---|---|---|---|---|
Speed Restriction Number | 1. 000128 | Restriction Information and Location | Between Quincy Center and Quincy Adams | Status | Removed |
Speed Restriction Number | 2. 000132 | Restriction Information and Location | Between Andrew and JFK/UMass | Status | Removed |
Speed Restriction Number | 3. 000129 | Restriction Information and Location | Between North Quincy and Wollaston | Status | Removed |
Speed Restriction Number | 4. 000131 | Restriction Information and Location | Between JFK/UMass and North Quincy | Status | Removed |
A variety of other in-station work also took place along the Orange Line to further enhance the rider experience, including:
- cleaning, sanding, and painting wooden station benches;
- fire retardant installations;
- station painting;
- door repairs;
- yellow tactile edging repairs to platforms;
- flooring repairs to prevent tripping hazards;
- concrete repairs;
- stairway upgrades and repairs, including handrail repairs;
- waste receptacle replacements;
- powerwashing and cleaning work; and
- installing/replacing station signage, including system maps.
More Information
Media Contact Information
For all queries and comments, please contact:
Recent News on the T
November 21, 2024
November 15, 2024
November 14, 2024
November 13, 2024