See Red Line Work We Completed November 15 – 17

Updated on November 20, 2019

A crew member replaces a light fixture at Downtown Crossing as part of the Red Line beautifucation and track work during the November 15 – 17 weekend shutdown

During 4 weekend shutdowns from November 15 – December 15, 2019, we closed sections of the Red Line to work on track replacement and station improvements. These closures allowed us to complete work at Park Street 4 months earlier than planned and at Downtown Crossing 11 months earlier than planned.

This project, in conjunction with slab replacements we’re working on in 2020, will keep the tracks in a state of good repair and will support the new Red Line vehicles coming into service.

We thank you for your patience during these closures.

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Weekend 1: What We Completed

During the first weekend shutdown, our crews replaced 478 feet of track and 460 feet of third rail on Downtown Crossing’s northbound side.

We also:

  • Installed new tactile warning strips on Downtown Crossing’s southbound platform and on Park Street’s northbound platform.
  • Installed new vinyl signs on Downtown Crossing’s northbound and southbound platforms.
  • Filled 2 ceiling voids and repaired stair leaks at Downtown Crossing.

Photo Gallery

Related Updates

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects