Green Line Transformation Weekly Progress Update: November 28 – December 3
Updated on December 2, 2021
GLT projects will improve safety, reliability, and access for Green Line riders and the surrounding communities.
Last week, work continued on the following projects:
- D Branch Track and Signal Replacement – 99% complete
- Lechmere Viaduct Rehabilitation – 98% complete