Green Line Transformation Weekly Progress Update: September 5 – 10
Updated on September 10, 2021

GLT projects will improve safety, reliability, and access for Green Line riders and the surrounding communities.
Last week, work continued on the following projects:
- D Branch Track and Signal Replacement – 98% complete
- B Branch Station Consolidation – 82% complete
- Lechmere Viaduct Rehabilitation – 97% complete
Building a Better T
As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.
Related Projects

This project is one of many we're working on to ensure twice as many passengers have access to a safer, more comfortable, and more reliable Green Line by 2030.
Building a Better T
As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.
Related Projects

This project is one of many we're working on to ensure twice as many passengers have access to a safer, more comfortable, and more reliable Green Line by 2030.