Skip to main content
Menu

Gloucester Drawbridge Replacement Progress Recap, March – June 2022

Updated on September 7, 2022

View of train arriving at station

The MBTA is pleased to provide this project update on construction progress from March through June 2022. 

Return of Service

The MBTA re-opened the Gloucester Drawbridge on May 23, 2022, restoring service to Gloucester and Rockport Stations. 

See Newburyport/Rockport Line service alerts 

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

East Approach Spans 

In April, crews finished the removal of the temporary construction trestles which were used to support the gantry crane system and facilitate construction of the new bridge. The setting of the approach precast box beams was also completed in April.   

After the box beams were placed, the concrete deck was formed and poured over the frame.  

Workers smoothing concrete deck
Workers smoothed the new concrete deck after it was poured over the box beams.

Once the deck concrete was cured, waterproofing was applied. The ballast curbs, walkway, and railings were also constructed. 

Construction equipment installing bridge railing
Once the deck concrete was cured and waterproofed, crews constructed ballast curbs, the walkway and railings. This view shows the railing on the north walkway.

Pier 2 and Machinery Room 

Pier 2 houses the machinery needed to move the bridge. The access stairway to the machinery room was installed, along with access ladders and hatches. Millwrights and engineers took measurements and made fine adjustments to machinery and alignment of the northern bascule. Meanwhile, electricians worked on connecting power and controls to the machinery room.

Worker using machinery
Millwrights worked on the northern bascule machinery.

Track 2 Rail 

With the northern bascule span set in place, Track 2 (northern track) work began. At the west approach, crews installed the track leading up to the bridge structure.  

Workers on railway
Once the span was complete, northern bascule Track 2 work began.

Workers installed the track leading up to the west bridge approach. On the bridge structure, workers adjusted and aligned the rail joints. East of the draw span, track was installed over the deck-over-counterweight beams.  

Construction equipment installing bridge railing
Rails being installed on the northern bascule.

The deck-over-counterweight beams span over Pier 2, the trunnion pier, and support the track above.   

Signals, Controls & Power 

The testing of the signal system to support the return of trains on the southern structure and Track 1 (south track) was completed. For the northern bascule, work has progressed in connecting the power and controls from the machinery room at Pier 2 to the control tower.

Construction workers install support brackets
Support brackets for conduit were installed along the bridge.
Conduits along bridge
Conduits were run from the machinery room to the control tower.

West Abutment & Fender System 

The granite stone masonry of the west abutment was grouted and repointed.  

view of granite stone masonry abutment
A view of the abutment granite stone masonry after grouting and repointing. The abutment is protected by fender boards.

Crews have been working at low tides to install the remaining bottom fender boards.  

Fender board construction on pier
Workers installed the bottom fender boards during low tide.

The fender platform adjacent to Pier 2 was completed. 

Upcoming Work

  • Remaining Track 2 work
  • Bridge controls testing of northern bascule 

For More Information

If you have questions or comments, please email the team at GloucesterDraw@MBTA.com.

 

Related Projects

View all projects

Get Involved

Sign up to receive email advisories and meeting notices.

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects

Get Involved

Sign up to receive email advisories and meeting notices.