Skip to main content
Menu

Gloucester Drawbridge Replacement October 2021 Progress Recap

Updated on November 19, 2021

Workers are shown on a boom lift above the observation level of the control tower. Another worker stands at the bottom of the boom lift. A yellow crane is parked next to the control tower at right, and another crane can be seen behind the tower.
Roof panel being installed on the observation level of the control tower

The MBTA is pleased to provide an update on ongoing and completed project activities, as well as a preview of upcoming work. 

Although the project remains on schedule, supply chain delays and bridge construction complexities have delayed the opening of the southern barrel. As we evaluate alternatives to restore rail service as soon as possible, work crews are using this opportunity to accelerate other projects planned for the line. We’ll notify the project email list and the local press when a new reopening date is available. 

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Control Tower

Workers continue to prepare the control tower to operate the new bridge. Roofing panels are being installed over the observation level of the tower, and plumbing is being installed within the control level.

The interior of control level of the control tower is shown during construction. Plywood floors and wooden ceiling rafters are shown, as are floor-to-ceiling metal structures enclosing plumbing. Construction materials are on the floor, and an orange construction crane can be seen outside the window at the rear.
Plumbing installation at the control level of the control tower

Workers are preparing the interior of the control tower for drywall installation.

A worker in a bright yellow shirt and hard hat installs foam insulation panels in the walls of the control power, just below below a bright bulb suspended from an overhead I-beam
Installation of insulation within the control tower

Piers 2 and 3

Precast footing panels are being installed at Piers 2 and 3. The formwork is being removed from the previously constructed south footing so that existing footings on the north side can be connected.

Three workers in safety vests stand on a small wooden boat on the water next to the bridge. They are cleaning the formwork from the bridge's south footing.
Cleaning the formwork from the south footing

Precast poured-concrete panels for the footings have been delivered to the site and installed. 

A large, rectangular, poured-concrete footing panel is shown resting on a plywood structure near the water before placement and installation.
A precast footing panel after delivery and before placement and installation
One of the large poured-concrete footing slabs is shown suspended in the air. A large circle cut out of the middle of the footing is centered over a large cylindrical pier, around which the footing panel will be lowered into place.
Lifting one of the footing panels for installation
Five workers stand on (or on ladders resting on) a precast, poured-cement footing panel just after it has been lowered into place. Suspension cables are still attached to the footing.
Installing a footing panel during low tide

We are installing a fender system in the channel to protect the bridge from damage caused by vessels moving underneath. 

A fender system designed to protect the bridge from impacts by vessels moving underneath is installed in the channel. A worker dressed in orange stands near wooden planks in the process of being placed horizontally above the water, perpendicular to the tall wooden pilings that support them.
Installation of the fender system in the channel

Signals, Power, and Utilities

Crews have begun pretesting control tower operation of the bascule span. They are operating the bridge using the main drive and control panel during testing. Continuing installation of the signal system includes connecting all signal instrument houses and signal instrument rooms together.  

Workers are also installing the framework for the walkways around the signal instrument rooms and the control tower. 

A steel frame is shown under construction around the exterior base of the signal instrument room. A concrete foundation can be seen below the frame.
Installing the frame for the walkway around the signal instrument room

Get Involved

Sign up to receive email advisories and meeting notices.

Upcoming Work

  • Continued installation of drywall, electric service, and plumbing inside the control tower
  • Continued fender system installation
  • Witness testing of the new equipment and systems

For More Information

If you have questions or comments, please email the team at GloucesterDraw@MBTA.com.

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Get Involved

Sign up to receive email advisories and meeting notices.

Related Projects

View all projects