Gloucester Drawbridge Replacement February 2021 Progress Recap

Updated on March 4, 2021

Reinforcing for the abutment approach slabs being installed
Reinforcing for the abutment approach slabs being installed

The MBTA is pleased to provide you with this update of project activities completed in February and ongoing or upcoming work for March 2021. 

East Abutment

The construction of the northeast retaining wall is complete. The east abutment was backfilled and compacted up to the level of the approach slabs. An approach slab spans the gap between the rigid abutment and the approach embankment. The slab reduces the load on the abutment along with reducing the potential for settlement of the tracks leading up to the bridge. The concrete approach slabs were formed, reinforced, and poured. After the approach slabs were cured, compacted fill was placed over them.

Completed approach slabs at the east abutment
Completed approach slabs at the east abutment

Control Tower

Progress has been made on the new control tower, which will operate the new bridge. Critical electrical and signal panel cabinets have been installed. System controls including power drive units and motor control center units have been installed inside the tower.

Pier 1

Pier 1 will be supported on two drilled shafts. The drilled shaft rig and barge are mobilizing and will soon begin installation of the drilled shafts. Steel casings and drilling equipment including augers have arrived on site.

Drilled shaft casings arrive on site
Drilled shaft casings arrive on site

Pier 2

Work has progressed on Pier 2, which will hold the trunnion tower (an axel that supports the bridge span) and the machinery for the new moveable bascule span. The rear and front reinforced concrete walls are complete.

Pier 2
Pier 2

West Causeway

The installation of a steel sheeting wall for support along the south side of the west causeway has begun. This wall will support the relocated southern track.

Installation of west causeway sheeting wall
Installation of west causeway sheeting wall

Signals, Power, and Utilities

The installation of conduits towards the east of the bridge has continued along with the installation of new precast hand holes that provide access to the infrastructure. These conduits will support vital MBTA signal systems and provide additional capacity for future upgrades.  At the generator pad, new cabinets were installed to support the generator.

Installation of conduits east of bridge
Installation of conduits east of bridge
Generator cabinet installation
Generator cabinet installation

 

Coming in March 2021 

  • Pier 1 - drill shafts will be constructed.
  • West Causeway - work will continue on the retaining wall along the south side for the relocated southern track.

Related Projects

View all projects

Get Involved

Sign up to receive email advisories and meeting notices.

Related Projects

View all projects

Get Involved

Sign up to receive email advisories and meeting notices.