Gloucester Drawbridge Replacement December 2021 Progress Recap
Updated on January 25, 2022
Note: Beginning with this edition of the newsletter, we will move to quarterly updates. The next update will appear in April 2022.
The MBTA is pleased to provide an update on ongoing and completed project activities, as well as a preview of upcoming work.
Although the overall project remains on schedule, supply chain delays and bridge construction complexities have delayed the opening of the southern barrel. We now anticipate that single-track service to Rockport will be restored in late May 2022. We’ll notify the project email list and the local press when the new reopening date is available.
Control Tower
Work on the control tower continues. With key equipment already installed in the electrical, signal, and control rooms, the focus of the work is now on finishing the interior of the tower.
We have installed the control tower’s HVAC systems.
Plumbing installation is progressing in the restroom, kitchenette, and mop sink.
In the tower, we have installed and finished the drywall.
In addition, electricians have wired outlets and lighting fixtures.
Pier 2
Pier 2 contains the trunnion tower that supports the movable bascule span. This pier also houses the machinery needed to move the bridge. We have completed the southern section of the pier, and it now supports the operational southern bascule. The focus is now on completing the northern section of the pier, which will support the northern bascule.
Workers have formed and poured the northern portion of the reinforced concrete pier cap.
After the pier cap was formed and poured, we formed the machinery platform and rear walls and installed reinforcement.
Movable Bascule Span
We conducted controls testing of the southern bascule span. To ensure that the bridge functions properly, we tested it under normal operations, as well as under a variety of other scenarios.
During testing we made fine adjustments to software, machinery, and other components of the bascule.
Upcoming Work
- Signal system testing
- Continued construction of the northern section of Pier 2, including completing the pier’s rear wall, front wall, and side wall
- Delivery and erection of the northern bascule span assembly
For More Information
If you have questions or comments, please email the team at GloucesterDraw@MBTA.com