Gloucester Drawbridge Replacement April 2021 Progress Recap
Updated on May 19, 2021
The MBTA is pleased to provide you with this update of project activities completed in April 2021 and ongoing or upcoming work for May 2021.
East Approach Spans
Crews started work on the east approach bridge spans, which lead to the river channel and moveable span.
The approach span superstructure consists of prestressed concrete box beams, which are precast and delivered to the site before being lifted and set into place.
After setting the box beams, crews installed the bridge deck reinforcing and poured concrete for the deck. They have also started constructing the concrete curbs that run along the deck edges, retain the track ballast, and support the walkways.
Control Tower
In the control tower, crews continued installation of new conduit and wiring of critical electrical, signal, and system controls equipment. They're connecting submersed cable and conduits that cross the river to the control tower raceways. Once completed, the new control tower will operate the bridge.
Pier 2
Crews continued work on Pier 2, which will hold the trunnion tower and the machinery for the moveable bascule span.
The trunnion tower columns have been installed. These columns support the trunnion, which supports the axle that the bascule span will rotate on.
Workers completed construction of the southern tie beam for Pier 2. This beam will support the walkway in addition to laterally supporting the pier walls.
Channel Work
Crews started installation of the new channel fender system, and timber fender piles have been installed at the bridge.
By coordinating with the USCG and harbormaster, we installed the piles while limiting the impact to the navigable river channel.
West Causeway
The installation of a steel sheeting wall is approximately 75% completed. This wall will support the relocated southern track.
Crews began work to modify and retrofit the existing control tower, which will be repurposed into a signal instrument room.
The southern barrel is tracking to reopen late summer 2021.
Signals, Power, and Utilities
Crews continued installing conduits towards the east of the signal instrument house (See Photo 12). These conduits support MBTA signal and fiber systems.
Work on leading the submersed cable and conduits to the new Control Tower continues.
Coming in May 2021
- Installation of the remaining fender piles and fender boards
- Modifications to the west abutment, including installation of the approach slabs that will lead up to the bridge
- Arrival and assembly of the moveable bascule span