Codman Yard Construction Update | August 24 – September 13, 2024
Updated on August 29, 2024
Construction activities will continue on the Codman Yard Expansion and Improvements project. Over the next three weeks, crews will work on track installation, duct banks, and the utility bridge.
Building a Better T
As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.
Construction Progress Update
Over the next three weeks, crews will:
- Continue work on track installation, duct banks for electrical conduits and manholes, and the utility bridge during weekdays and Saturdays, 7 AM – 3 PM
- Work 24 hours (6 AM – 6 AM) on track installation from Tuesday, August 27 – Thursday, August 29 and on Tuesday, September 3
There will be no construction happening on Sundays or Labor Day, September 2.