See Red Line Work We Completed December 13 – 15

Updated on December 17, 2019

Crew members replace track on Park Street's southbound side during the December 13 – 15, 2019, Red Line weekend shutdown

During 4 weekend shutdowns from November 15 – December 15, 2019, we closed sections of the Red Line to work on track replacement and station improvements. These closures allowed us to complete work at Park Street 4 months earlier than planned and at Downtown Crossing 11 months earlier than planned.

This project, in conjunction with slab replacements we’re working on in 2020, will keep the tracks in a state of good repair and will support the new Red Line vehicles coming into service.

We thank you for your patience during these closures.

Learn more about Red Line Maintenance Work

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Weekend 4: What We Completed

During the final weekend shutdown, our crews replaced 424 feet of track on Park Street’s southbound side.

We also completed work at Downtown Crossing:

  • Installed new rubber flooring in the Alewife passageway
  • Installed two new signs and repaired the wall on the Alewife platform
  • Repaired platform edges throughout the area

Related Updates

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects