Green Line Intersection Upgrades

A Green Line train passes over a newly completed intersection upgrade

Between 2019 and 2020, we will replace sections of track where the rail crosses the road and pedestrians, bicyclists, and drivers pass over the tracks.

Uneven pavement will be replaced with a new, smooth layer. Accessible ramps will be installed in several sidewalk locations. 

Why We’re Doing This Work

This project will bring Green Line intersection tracks into a State of Good Repair.

Where We’re Doing This Work

The work will primarily be on the Green Line B and C. We will also replace a section on the Mattapan Line. Additional locations may be announced in the future.  

Related Projects

Side view of new Green Line car at Riverside (July 2018)

This project is one of many we're working on to ensure twice as many passengers have access to a safer, more comfortable, and more reliable Green Line by 2030.

Learn more about the Green Line Transformation

When We're Doing This Work

green line C Green Line C
August 9 – 12, 2019

Intersection:
Summit Avenue and Beacon Street

bus Shuttles replace train service between St. Mary's Street and Cleveland Circle. Note: Shuttles start Friday at 8:30 PM. Regular service resumes Monday.

green line B Green Line B
August 17 – 19, 2019

Intersection:
Amory Street and Commonwealth Avenue
Buick Street/Saint Paul Street and Commonwealth Avenue

bus Shuttles replace train service between Blandford Street and Washington Street. Note: Shuttles start Friday, August 16, at 9 PM. Regular service resumes Monday.

What You Can Expect

We will demolish and reconstruct rails, install new rubber or asphalt road crossings, and pour new pavement at each of the crossings.

To do this work, we need safe access to the tracks and subsurface at each location. We plan to complete construction over approximately 17 weekends between June 2019 and May 2020, in coordination with other Green Line projects.

Photo Gallery

Contact Us

For all queries and comments related to Green Line Intersection Upgrades, please contact us at GLintersections@MBTA.com.

If you would like to report a noise issue, call the 24/7 hotline at 508-676-3598.

For More Information

Get project news, updates, and information delivered to your inbox.

MBTA Improvements

As part of our $8 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

Side view of new Green Line car at Riverside (July 2018)

This project is one of many we're working on to ensure twice as many passengers have access to a safer, more comfortable, and more reliable Green Line by 2030.

Learn more about the Green Line Transformation

MBTA Improvements

As part of our $8 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more